Power Sector ensures restoration of electricity supply to pre-earthquake levels and to provide necessary spares and human resources to enhance local capacities.

 

Brig (R) Pervez Hayat Niazi Director General

more contacts

Power Generation Strategy

Sector Updates

[Last updated on: Mar 01, 2010]

 

Total Projects: 16

Under Implementation: 16

 

 Stages  Upto June 08 % %
 Completed - - 6 37.50
 Under Construction - - 7 43.75
 Tendering - - - -
 Designing 13 81.25 3 18.75

 Total

13

81.25

16

100

 Overall Progress:                 June 08:  00%,                 Present: 81.25%

 