ERRA is reconstructing 306 destroyed health facilities in affected areas. The aim is to restore health infrastructure which is financially viable, easily accessible to vulnerable population with overall improvement in health status of the affected areas. The sector specifically, focuses on introducing new technology and equipment, improved service delivery, thus turning adversity into opportunity.

 

Brig (R) Pervez Hayat Niazi Director General

more contacts

 

 

Sector Updates

[Last updated on: Jan 01,2012]

•  To be Reconstructed: 306
•  Under Implementation: 306

 Stages  Upto June 09 % %
 Completed

60

19.54 173 56.54
 Under Construction 128 41.69 86 28.10
 Tendering Stage 38 12.38 41 13.40
 Designing Stage 81 26.38 6 1.96
 Total 307 100.00 306 100

* 137 Prefabricated structures already provided for continuity of service delivery

Overall Progress:                  June 09:  61.23%,           Present:  84.64%

 