ERRA is reconstructing 715 government buildings which
were totally destroyed due to the earthquake. For smooth
functioning of the government sector ERRA provided 704
prefabricated offices in affected areas and District
Complex Muzaffarabad has been handed over to the
Government of AJ&K.
|

Brig (R) Pervez Hayat Niazi
Director General |
|
more contacts |
|
|
[Last updated
on: Mar 01, 2010]
•
Buildings to be Reconstructed: 692
•
Under Implementation: 692
|
Status |
Upto
June 08 |
% |
 |
% |
|
Completed |
- |
- |
348 |
50.29 |
|
Under Construction |
49 |
6.85 |
314 |
45.38 |
|
Tendering |
- |
- |
22 |
3.18 |
|
Designing |
215 |
30.06 |
8 |
1.16 |
|
Total |
264 |
36.92 |
692 |
100 |
* 704 Prefabricated offices provided in affected
areas.
* District Complex Muzaffarabad handed over to
the Govt of AJ&K comprising 62 buildings and 92
residential houses
Overall Progress:
June
08:
6.85%,
Present:
95.67%
For further details view
Sectoral Update
|
|
|
|