ERRA is reconstructing 715 government buildings which were totally destroyed due to the earthquake. For smooth functioning of the government sector ERRA provided 704 prefabricated offices in affected areas and District Complex Muzaffarabad has been handed over to the Government of AJ&K.

 

Brig (R) Pervez Hayat Niazi Director General

more contacts

Governance Strategy

Sector Updates

[Last updated on: Mar 01, 2010]

 

•  Buildings to be Reconstructed: 692

•  Under Implementation: 692

 Status  Upto June 08 % %
 Completed - - 348 50.29
 Under Construction 49 6.85 314 45.38
 Tendering - - 22 3.18
 Designing 215 30.06 8 1.16

 Total

264

36.92

692

100

* 704 Prefabricated offices provided in affected areas.
* District Complex Muzaffarabad handed over to the Govt of AJ&K comprising 62 buildings and 92 residential houses

Overall Progress:                  June 08:  6.85%,           Present: 95.67%

For further details view  Sectoral Update

 