On
July 13, 2010 Deputy Chairman ERRA, Lt Gen
Muhammad Haroon Aslam, held a meeting with the
Chief Operating Officer, China Xinjiang Beixin (CXB)
Construction and Engineering Group, Mr. Zhao
Mingsheng. Brig Masuood Ahmad, Chief of Staff
ERRA, Mr. Hamid Yaqoob Sheikh, DG PIII ERRA, Mr.
Muhammad Sayyar, Director (Urban Development AJ&K)
and Ms. Sophie, Deputy Director CXB, were also
present in the meeting.
The Deputy Director CXB updated the Deputy
Chairman ERRA about the state of Priority –I
projects under City Development Projects, being
executed by CXB in three earthquake affected
districts of AJ&K. In Muzaffarabad, out of a
total of 11 projects, only one project is being
launched, remaining 10 projects are at various
stages of approval and designing. In Rawalakot
and Bagh, out of a total of 15 and 5 projects,
respectively, none has been launched, so far.
Showing his concern over slow progress of CXB,
Deputy Chairman ERRA particularly brought
following issues to the notice of CXB officials:
• Slow progress on Tahlee Mandi Road.
• Detailed designs and preparation of BOQs of
remaining projects are pending despite repeated
reminders.
• Detailed design of Hullar Bridge and Ring Road
is yet to be finalised. • The camp office of CXB
is yet to be established at Rawalakot.
• The survey work of nine projects is still to
be started.
Deputy Chairman desired that to accelerate the
pace of work following measures be initiated
without further loss of time:
• Four bridges, to be constructed by CXB, should
be launched at the earliest.
• The projects with no land issues and handed
over to CXB be taken up immediately.
• Designing of projects be expedited so that
physical execution can be started.
CXB assured Deputy Chairman that in the next two
months many projects including the bridges would
be launched in the three earthquake affected
districts of AJ&K.
|